West Virginia Business and Law - Project Estimating and Bidding Practice Exam
$9.99
{{option.name}}:
{{selected_options[option.position]}}
{{value_obj.value}}
10 Project Estimating and Bidding Questions Immediate download of pdf practice exam with question, answer, page number and formula calculation explanation. Your company leases a bulldozer for $1,000 per month. The bulldozer has a 20% excess capacity and you will only be using it 10% of the time during the month. Based on this information, determine what to charge your project for use of the bulldozer. A. $100B. $110C. $120D. None of the above